UKCW London: 7-9 May 2025 | ExCeL
UKCW Birmingham: 30 Sept-2 Oct 2025 | NEC

Press Releases

Industry agrees that lack of flame-retardant treatment for timber was inappropriate| Construction Buzz #222

19 Jun 2019

Following the serious fire at the Samuel Garside House development in Barking at the weekend, leading timber industry associations, the Timber Trade Federation (TTF) and Wood Protection Association (WPA), are clear that the failure to specify an industrial fire retardant pre-treatment for the timber balconies and cladding across the front of the building, was completely inappropriate in the circumstances.

The six-storey building in De Pass Gardens featured timber balconies, balcony dividers and extensive balustrading, so much so that it resembled and has been referred to as, timber cladding.  The lack of a flame retardant treatment combined with multiple small cross sections of timber with plenty of air movement around each panel, in our opinion created an unnecessary fire risk.

TTF and WPA collectively agree that treatment was essential in this situation, even though it would appear that this was not required by Building Regulations and the project was subsequently approved by Building Control.

TTF Managing Director Dave Hopkins stated that “If a comprehensive fire risk assessment had been conducted on this design it would have been clear that additional protection was required in these particular circumstances”.

It has emerged that the timber supplied for the project had a ‘Euroclass D, s2, d0’ reaction to fire rating. Flame retardant pre-treatments are readily available which could have upgraded the timber components to the more appropriate, much higher Class B rating. If that had been done, the timber decking and cladding would have performed very differently. Such industrial flame-retardant processes are subject to independent quality assurance under a well-respected scheme operated by the WPA.

Gordon Ewbank, WPA Chief Executive, added that “The privatisation of Building Control services in the UK does not help in these situations. Building Control service providers are nervous about specifying standards higher than strictly required by Building Regulations (even if appropriate as was the case at Barking), in case the contractor switches to another service provider who will approve the design at the lower standard and cost. Indeed, this point was also highlighted in the Hackitt review in the aftermath of the Grenfell tragedy”.

In conclusion, flame retardant treated wood cladding has proved fit for purpose over many years of successful service around the world and continues to meet the requirements of UK Building Regulations. If pre-treatment had been carried out in this case, the timber decking and cladding would have performed very differently.

Back to Top
Loading

Birmingham Sponsors

Partners

Previous Attendees